Main Street Construction Project - Update on October 13, 2018

Construction is progressing well with a completion date of October 31, 2018. Interlock is expected to be finished by October 19, 2018.

The construction team continues to meet with the engineer and municipal staff every two weeks to discuss any issues. These meetings are generally followed by a “walk about” of the site to give staff and engineer first-hand understanding of the progress.

All asphalt work should be completed by October 31th, 2018, possibly earlier if the weather cooperates. Communication with CN Rail will determine when construction near the rail tracks can be done. Canada Post deliveries have been re-routed through the municipal parking lot for the time being.

SUNDRIDGE LIONS' CLUB
ALL CANDIDATES
MEETING


Sundridge & Strong Council
Candidates Meeting
SSJ Arena
Monday, October 1, 2018 @
7:00 p.m.

"Sundridge, Ontario" Facebook

The Village of Sundridge has administrative responsibility for the "Sunny Sundridge" Facebook page and not the "Sundridge Ontario" page. Control over content for that page is not within the Village of Sundridge jurisdiction. Dawn Berry is not a representative of the Village of Sundridge.

The Village of Almaguin are in the middle of a public engagement process
for the Almaguin Regional Economic Development Plan and would like public
feedback. Please complete the survey provided and submit to the Village of
Sundridge Municipal Office before 4:00 p.m. on Friday, July 6, 2018 or
complete the on-line survey at the link provided.
https://www.surveymonkey.com/r/Almaguin

PDF Document: Community Feedback Survey

Best online roulette for money https://onlineroulette.money/